NewsQuick take1 min readDisconfirmAI Editorial

South Korean HVAC Firm Ottek Carrier Signs MOU to Supply Cooling Equipment for 200MW Sacheon AI Data Center

Ottek Carrier has signed a three-party memorandum with developers to provide cooling and HVAC equipment for the planned 200MW Sacheon Skycity AI Data Center in South Korea, with Phase 1 targeting February 2028.

2026-11-18 09:02 GMT+8

South Korean heating, ventilation, and air conditioning (HVAC) company Ottek Carrier announced on November 18 that it has signed a three-party Memorandum of Understanding (MOU) with Taewang D&D and J&J First Holdings. The agreement aims to secure the supply of cooling and HVAC equipment and technical support for the 'Sacheon Skycity AI Data Center' project in Sacheon, Gyeongsangnam-do.

The data center is planned with a total capacity of 200 megawatts (MW), divided into two phases: Phase 1 (80 MW) targets the start of trial operation and verification in February 2028, while Phase 2 will add 120 MW. Under the MOU, Ottek Carrier will coordinate equipment specifications, quantities, and production schedules aligned with the Phase 1 timeline, providing technical support during installation and commissioning. Specific contract values and final equipment quantities remain undisclosed.

This move marks the latest step in Ottek Carrier's expansion into the large-scale AI infrastructure sector. Previously, the company won a contract to supply chillers for a 48 MW hyperscale data center in Incheon and was selected as the preferred bidder for cooling equipment at the 200 MW Gumi AI Cluster Data Center in North Gyeongsang Province.