NewsTopic · 韩国AIDC电网标准Material1 min readDisconfirmAI Editorial

KT Warns Submarine Cable Capacity Gap Hinders South Korea's AI Data Center Goals

KT executive states South Korea's planned 18.4GW AI data centers require ~1700Tbps international bandwidth, but only 200Tbps is planned, urging public-private expansion.

2026-10-26 15:56 GMT+8

Jeon Myung-jun, head of Enterprise Services at Korean telecom giant KT, stated at a National Assembly symposium on "Gangwon AI Infrastructure Hub Strategy" that current submarine cable infrastructure is insufficient to support South Korea's ambition to become a global AI hub, despite the government's plan to build 18.4GW of AI data centers (AIDCs) by 2035.

According to KT's estimates, each 1GW of AIDC generates approximately 91Tbps of traffic, meaning the 18.4GW target would require about 1700Tbps of international transmission capacity. In contrast, the submarine cable capacity operational or planned through 2030 is only around 200Tbps, leaving a deficit of over 1500Tbps. Jeon emphasized that without adequate export channels, large data centers would remain mere "warehouses."

As AI usage shifts from training to inference, the demand for real-time data exchange has increased, highlighting the importance of international connectivity. South Korea currently operates only 8 global submarine cables, far fewer than Japan's 43 and Singapore's 34. Jeon proposed forming a public-private consortium involving telecom operators, tech giants, financial investors, and the government, along with diversifying landing station locations, to address this bottleneck.

Sources

  • zdnet.co.kr↗
Sign in / Sign up
ReadingResearchRadarInvestment framework
Topic

韩国AIDC电网标准

韩国气候能源环境部计划于2026年底出台AI数据中心(AIDC)专用电网接入标准(Grid Code),旨在应对GW级算力设施带来的毫秒级电力波动风险。然而,这一新规与禁止LNG直购的政策叠加,引发业界对已开工项目延期及成本激增的担忧。与此…

5 steps2 piecesUpdated 2026-10-27 11:06

How it got here

  1. 2026-04-29韩国电力公社(KEPCO)系统规划负责人郭恩燮在论坛上提出需为大型数据中心建立电网代码标准,以应对AI负载剧烈波动导致的电网稳定性问题。m.ajupress.com ↗
  2. 2026-05-07韩国国会通过《AIDC特别法》,但应气候部要求,删除了允许数据中心直接向LNG发电厂购电的条款,强制其使用国家公共电网。zdnet.co.kr ↗
  3. 2026-08-25韩国气候部官员证实,将在年内推出针对维持稳定负载模式的AIDC的电费折扣方案,并制定包含最低设备要求的专用电网代码。en.sedaily.com ↗

What is still unsettled

  • 气候部最终出台的电网代码是否会对已获批或在建的项目设置过渡期豁免?
  • 政府是否有具体时间表和资金计划来支持海底电缆的公私合营扩建?
  • SKT等运营商提出的税收优惠诉求能否在现行税法框架下得到落实?

Also in this thread

  • South Korea Plans Dedicated Grid Standards for AI Data Centers; Lawmaker Warns of Delays for GW-Scale Projects2026-10-21