AEP Global Commercial Director Gavin Wight: High-Voltage Commissioning for AI Data Centers Must Be Engaged as a Separate Discipline from Day One

Gavin Wight, Commercial Director at AEP Global, argues that the demand for direct high-voltage connections in AI data centers has pulled substations, power transformers, and protection systems—previously outside project boundaries—into critical power architecture. Because high-voltage commissioning differs fundamentally from low-voltage verification in safety protocols, testing methods, and standards, it cannot be simply folded into existing scopes; delaying professional engagement until infrastructure nears completion risks closing windows for design decisions, interface coordination, and resource locking.

2026-11-19 03:33 GMT+8

The power demands of AI data centers are pushing projects into territory many developers have not fully prepared for. As computing capacity grows and rack densities rise to unprecedented levels, facilities are demanding power supplies measured in tens or even hundreds of megawatts. Gavin Wight, Commercial Director at AEP Global, points out that as AI data center development trends toward gigawatt-scale demand, local distribution networks in some markets can no longer support new projects without major upgrades. This has extended approval processes, with some projects facing multiyear delays. Direct connections to 66kV, 110kV, or 150kV transmission networks are becoming an increasingly attractive alternative, but this simultaneously brings substations, power transformers, HV cables, switchgear, protection systems, and grid interfaces into the project's critical power architecture—elements that, just a few years ago, would have sat entirely outside the project boundary.

Wight’s core argument is that high-voltage (HV) commissioning is not an extension of low-voltage (LV) verification, but a separate engineering discipline. At higher voltage levels, electrical hazards include arc flash, flashover, and fatal electric shock, which can be lethal even when personnel do not directly contact live conductors. The consequences of incorrect protection settings or switching procedure errors can be equipment damage, grid disturbances, and severe project delays. HV commissioning has its own standards, testing methodologies, and safety protocols: transformers require electrical testing to confirm insulation integrity and winding condition; HV cables and terminations need verification of insulation performance and installation integrity; switchgear and circuit breakers require dual mechanical and electrical verification; and protection relays must undergo secondary injection testing against approved protection studies and setting schedules.

Sign in / Sign up
ReadingResearchRadarInvestment framework

He further argues that completing individual equipment tests does not automatically prove the entire HV installation is ready for energization. Before energization, the commissioning team must confirm that all inspections, tests, defect resolutions, and safety checks have been completed and appropriately authorized. This includes confirming protection settings, verifying switching schedules, checking grounding arrangements, and ensuring that required permits, procedures, and personnel authorizations are in place.

Wight identifies one of the greatest risks in large-scale data center development as treating HV commissioning as a late-stage activity, introduced only when the substation and associated infrastructure are nearing completion. By that stage, the window to influence design decisions, resolve interface issues, and lock in specialist resources may already have closed. He lists specific benefits from engaging HV commissioning teams from day one: participating in design reviews, establishing test requirements, identifying access and testing constraints, and coordinating responsibilities among supply chain parties more effectively.

It should be noted that Wight’s company is a specialized provider of HV electrical services, commissioning, and Safe Systems of Work, so positioning HV commissioning as a separate discipline requiring early intervention objectively supports its business model. However, the testing protocols and safety requirements he describes reflect industry-wide practices in electrical engineering, while his strategic advice on project timing and scope separation constitutes professional judgment.

Wight concludes that as data center power demands continue to grow, HV connections will likely become an increasingly common feature of digital infrastructure. Successfully managing this transition requires establishing a rigorous, specialized commissioning verification layer across the entire power chain—from the transmission interface to facility distribution—with confirmation both before and after energization. Treating HV commissioning as a dedicated discipline rather than an extension of LV verification is a crucial step toward safely, reliably, and on schedule meeting the construction demands of the AI boom.