NewsThema · AI数据中心电网瓶颈Wesentlich1 Min. LesezeitDisconfirmAI Redaktion

Goldman Sachs: Global data center power demand to rise 170% by 2030, US grid delays cited as biggest AI bottleneck

Goldman Sachs warns that despite massive AI capex, US grid interconnection delays averaging 5 years and local opposition could slow investment returns.

2026-10-21 07:15 GMT+8

In a report published on October 19, Goldman Sachs warned that the pace of power infrastructure expansion is failing to keep up with the rapid growth of the artificial intelligence industry, identifying it as the primary bottleneck for AI development. The report projects that global data center power demand will surge by 170% between 2025 and 2030, with more than 60% of this increase occurring in the United States.

Currently, approximately 2,600 gigawatts (GW) of generation and energy storage projects in the US are waiting for grid interconnection, a capacity more than double the existing installed base. However, the median time from application to commercial operation is about five years. Additionally, the construction of new high-voltage transmission lines has slowed significantly, environmental permitting takes three to four years, and supply chains for large transformers face delays of three to five years.

Local community opposition also poses a significant hurdle. Since January, 86 related projects have been cancelled or severely delayed, with 76 of these directly linked to resident concerns over noise, traffic congestion, water usage, and potential electricity price increases. Goldman Sachs estimates that total investment in AI computing, data centers, and power infrastructure will reach approximately $7.6 trillion between 2026 and 2031. Persistent power constraints could extend the payback period for these massive investments.

Quellen

Anmelden / Registrieren
LesenForschungRadarAnlageframework
etnews.com
↗
Thema

AI数据中心电网瓶颈

AI数据中心扩张的最大瓶颈已从资本或芯片供应转向电网接入能力。高盛与GlobalData等机构指出,全球数据中心电力需求预计2030年将激增170%,但美国电网平均接入延迟长达5年,韩国拟出台专用电网标准亦引发项目延期担忧。为应对“幽灵”需…

4 Schritte4 BeiträgeAktualisiert 2026-11-06 09:13

Wie es dazu kam

  1. 2026-10-21高盛发布报告预测,2030年全球数据中心电力需求将增长170%,美国电网接入平均需5年,成为AI扩张最大瓶颈。etnews.com ↗
  2. 2026-10-21TechRadar报道,美国公用事业公司为剔除投机性“幽灵”数据中心,要求提供财务担保和长期合同,导致约50%的规划项目被推迟或取消。techradar.com ↗
  3. 2026-10-21ZDNet Korea报道,韩国气候部拟年底出台AI数据中心专用电网接入标准,议员警告此举叠加LNG直购禁令,将使已开工的GW级项目面临设计变更与投资延期风险。zdnet.co.kr ↗

Was noch ungeklärt ist

  • 美国公用事业公司收紧准入后,实际落地的数据中心容量与申请量之间的差距是否会持续扩大?
  • 韩国拟议的专用电网标准具体技术门槛何时正式公布,对现有在建项目的追溯适用性如何界定?
  • 科技巨头通过自建电源或购买碳信用抵消电力短缺的策略,能否在2027年前有效缓解局部电网压力?

Auch in diesem Thread

  • GlobalData: Grid Delays Push Data Center Construction Timelines Beyond Two Years2026-11-03
  • South Korea Plans Dedicated Grid Standards for AI Data Centers; Lawmaker Warns of Delays for GW-Scale Projects2026-10-21